Monday, May 19, 2008

SURVEYING DOCUMENTATION (TCFSPP) PROJECT

DGPS BASE STATION SETUP FOR BATHIYMATRIC SURVEY.

TIDAL MEASUREMENT

HIDROGRAPHIC SURVEY EQUIPMENT SETUP ON BOARD

DGPS BASE ANTENA WITH SURVEY BOARD AS A BACKGROUND








BENCHMARK VERIFICATION AND ESTABLIHMEN NEW BENCHMARK



PRELIMINARY SURVEY (TOPOGRAPHY SURVEY)









SURVEY NEAR TRAFIC




SETTING OUT

LAYOUT OF (TCFSPPP) PROJECT:

MAIN LAYOUT OF PROJECT: Commencement date of project is March 2004 and finish on September 2006. This work are Civil Work, Building and Piling Package





ALL OVER VIEW ENTIRE PROJECT AREA AFTER COMPLETION WORK.


MAIN AREA OVERVIEW AFTER COMPLETION WORK

VIEW OF FLY OVER, SWITCHYARD, CONTROL BUILDING. AFTER COMPLETION WORK.

PILING WORK (TCFSPPP) PROJECT:


BORED PILE LAYOUT FOR COAL SILO

Bored Pile Diameter is 1000mm
Number of Bored pile is 600 Nos






PILING LAYOUT
For Boiler Foundation
Using Steel Pipe Pile
Diameter : 600mm
Depth : 50m
Number of Pile : 350 Nos



PILING LAYOUT
For Power House Foundation
Using Steel Pipe Pile
Diameter : 600mm
Depth : 50m
Number of Pile : 415 Nos







BORED PILE WORK With 1.0m Diameter and 40m Depth










Pouring Concrete for Bored Pile









Pile Load Test:






Pile Driving (Concrete Pile)
Used Diesel Hummer. With Varies of diametre
(300,350,400,500)mm

BUILDING CONSTRUCTION (TCFSPPP) PROJECT:


Front view of Administration Building Construction 4 stories.
(Tarahan Coal Fire Steam Power Plat Project)














Side view of Administration Building Construction 4 stories.
(Tarahan Coal Fire Steam Power Plat Project)

Sunday, May 18, 2008

Project Experience-4 (TCFSPPP)CHIEF SURVEYOR

February 2004 To May 2006

TOA CORPORATION - PT.ADHI KARYA (Joint Operation)

Jakarta,Indonesia



TARAHAN COAL FIRED STEAM POWER PLANT PROJECT,

CIVIL WORK AND PILING --- (LAMPUNG INDONESIA)


As a CHIEF SURVEYOR


Preliminary Survey for Construction

  • Benchmark Verification
  • Determining Benchmark Coordinate Value using Total Station.
  • Determining Benchmark Elevation Value using Auto level.
  • Hydrographic ( Bathymetry) Survey for Discharge Outlet Area.
  • Topographic Survey
  • Cross Section Work

Construction Work
  • Piling Work (PC Pile) Dia 300mm, 400mm, 450mm, 500mm for building Foundation (2500 Nos).
  • Piling Works (Steel Pipe Pile) Dia 612mm (1500 Nos) for Turbine Generator and Power House Foundation
  • Bored Pile Work Dia 1000mm,800mm (700 Nos)
  • Construction of Circulating Sea Water Pump Pit (Underground Structure)
  • Construction of Administration Building 5th floor.
  • Construction of Balance of Plant Building 4th floor.
  • Construction of Intake tunnel 3x4x600 meter, Underground Structure.
  • Construction/Installation of Corrugated Steel Pipe Dia 3.1 meter and 2.2 meter, 1200 meter long (underground pipe) for Discharge Outlet.
  • Construction of Fly Over Bridge for coal transportation.
  • Construction of Road inside Power Plan Area 4000 meter length.
  • Construction of Ash Disposal Area 12 Hectare, cut, fill and embankment.
  • Construction of Pipe Sleeper.
  • Construction of Oil Storage Tank Found.
  • Construction of Water Storage Tank.
  • Construction of Drainage System inside Power Plan using Hume Pipe.
  • Construction of Waste Waste Water Storage Pond.
  • Construction of Oil Storage Tank Foundation.
  • Responsible 8 Team of Surveyor.


Project Experience-3 SURVEY ENGINEER

February 2006 To April 2006

ADHI KARYA.PT ------------ Aceh, Indonesia

URGENT RECOVERY OF THE WEST COAST ROAD

BANDA ACEH AND MEULABOH PROJECT (CALANG MEULABOH SECTION )

KM. 155+630 to KM 270+000.

**AFTER TSUNAMI DISASTER..


As a SURVEY ENGINEER



Preliminary Survey for Construction

  • Establishment New Benchmark
  • Determining Benchmark (Establishment New Benchmark) Coordinate adjusted Value using Total Station 120 KM.
  • Determining Elevation and adjusted Value using Auto level 120 KM .
  • Cross Section work (Drawing).
  • Topographic Survey.
  • Road alignment and Structure layout.
  • Fixing of Bridge and Road Alignment
During three month period the main job is to make verification of benchmark that fixing by another party. Make new measurement for Control Point (Benchmark) with three dimension coordinate for approval to engineer. Topographic survey along proposed alignment using Total Station for design plan. Design of Road Alignment (horizontal & vertical) and applied the design to site.

Surveying Picture (ADB PROJECT)

GPS Survey, used for benchmark verification. Establishment New Control Point (Benchmark) by post Processing.






Total Station Survey, topographic survey, benchmark verification and Establishment new Benchmark, Setting out and construction survey work .






Survey Near Rail Road/trafic using Total Station.









Leica Laser Sprinter for Leveling work.